You must be extremely experienced with MS Project / Primavera software (or similar)

You will need to understand how to create an “Overall Project S Curves” in MS excel.

This task will be used to teach me how this works. Please keep it basic and explain any complex formulas. There are a number of tasks, this is Task 1.

Task 1

Fully populate the attached “Overall Project S Curves” excel spreadsheet.

This includes leaving all formulas in place so I can understand how the outcome was achieved. (Comments also may be needed to explain where the values came from)

The Progress to date has been saved from MS Project, the data date is the 18/02/2016

Spreadsheet Tabs:

Baseline Data –

- Populate the calendar/table with values and Cumulative Forecast Plan % at the base

Actual Data

- Use the Progress to date to assist with your workings (Make sure your actual is not the same as Baseline so it is easy to see)

Forecast Data

- Populate based on your other data

Chart

- Populate based on your other data

Project is required ASAP.

Use this code ”7/0\4” in your reply so know you have read this task brief fully.

Thanks for your time.

Excel Microsoft Lập kế hoạch dự án

ID dự án: #11341679

Về dự án

12 đề xuất Dự án từ xa Aug 23, 2016 đang mở

12 freelancer chào giá trung bình$174 cho công việc này

Teloquence

7/0\4 - EXCEL/VBA expert at you service. Consider it done. Check my past reviews for your reference. Eagerly waiting for your reply so that i can start with the implementation.

$200 AUD trong 2 ngày
(331 Nhận xét)
7.7
nimesha1994

”7/0\4” Hi, I'm very interested to do your project. I have great knowledge on about your project. I have already read your description and I feel like I would be a great fit for the project. I can start your proj Thêm

$55 AUD trong 2 ngày
(6 Nhận xét)
4.2
MaharNadirAli

A proposal has not yet been provided

$150 AUD trong 2 ngày
(9 Nhận xét)
3.2
prashantssingh

I have seven years of experience in MS Project tool (version 2003-2013 online) and three years of experience in project management. I provide project server support & provide guidance on Portfolio & Project planning. Thêm

$155 AUD trong 3 ngày
(1 Nhận xét)
2.2
ANIRWAN1991

Experience: 18 years in multi-sector projects with elaborate experience in Earned Value Analysis Qualification: 1. MTech in Construction Management from IIT Madras, 2. Project Management Cert Thêm

$150 AUD trong 3 ngày