- Latest available (Revised)
- Original (As enacted)
There are currently no known outstanding effects for the Energy Act 2023, Section 163.
Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.
(1)The ISOP must carry out its functions in the way that it considers is best calculated to promote—
(a)the net zero objective;
(b)the security of supply objective;
(c)the efficiency and economy objective.
(2)The net zero objective is the objective of enabling the Secretary of State to meet the duties imposed by—
(a)section 1 of the Climate Change Act 2008 (net UK carbon account target for 2050), and
(b)section 4(1)(b) of that Act (UK carbon account not to exceed carbon budget).
(3)The security of supply objective is the objective of ensuring the security of supply, to existing and future consumers, of—
(a)electricity conveyed by distribution systems or transmission systems, and
(b)gas conveyed through pipes.
(4)The efficiency and economy objective is the objective of promoting—
(a)efficient, co-ordinated and economical systems for the distribution and transmission of electricity and the conveyance of gas;
(b)efficiency (including the efficient use of energy) and economy on the part of persons who carry out relevant activities within subsection (5)(a), (b) or (c).
(5)In this Part, “relevant activity” means any of the following, so far as carried out in the course of a business—
(a)an activity mentioned in section 5(1) of the Gas Act 1986 (gas transportation, interconnection, supply, shipping, system planning, smart meter communication, code management);
(b)an activity mentioned in section 4(1) of the Electricity Act 1989 (electricity generation, transmission, distribution, supply, interconnection, multi-purpose interconnection, system operation, smart meter communication, code management);
(c)an activity, other than an activity within paragraph (a) or (b), in respect of which the ISOP has functions;
(d)an activity, other than an activity within paragraph (a), (b) or (c), that is connected with—
(i)the production, conveyance, storage or supply of energy,
(ii)the reduction of UK emissions of targeted greenhouse gases arising from the production, conveyance, storage, supply or consumption of energy, or
(iii)data relating to any matter within sub-paragraph (i) or (ii), or to demand for or consumption of energy.
(6)For the purposes of subsection (5)(d)—
(a)“energy” means energy in any form and includes fuel or other substances used to produce energy;
(b)references to the production of energy include references to the conversion of energy from one form to another;
(c)references to the supply of energy include references to adjusting consumption of energy (whether generally, at particular times, or by particular persons);
(d)an activity referred to in paragraph (d)(i) is not a relevant activity when carried out in relation to products for human or animal consumption;
(e)“UK emissions of targeted greenhouse gases” are emissions of such gases as are, or are treated for the purposes of Part 1 of the Climate Change Act 2008 as, emissions from sources in the United Kingdom.
(7)In this section, “targeted greenhouse gas” has the same meaning as in Part 1 of the Climate Change Act 2008 (see section 24 of that Act).
Commencement Information
I1S. 163 not in force at Royal Assent, see s. 334(1)
I2S. 163 in force at 31.1.2024 by S.I. 2024/32, reg. 3(a)(ii)
The Whole Act you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Act you have selected contains over 200 provisions and might take some time to download.
Would you like to continue?
The Whole Act without Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Act without Schedules you have selected contains over 200 provisions and might take some time to download.
Would you like to continue?
The Whole Act you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Act without Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.
Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.
Text created by the government department responsible for the subject matter of the Act to explain what the Act sets out to achieve and to make the Act accessible to readers who are not legally qualified. Explanatory Notes were introduced in 1999 and accompany all Public Acts except Appropriation, Consolidated Fund, Finance and Consolidation Acts.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: