The term provision is used to describe a definable element in a piece of legislation that has legislative effect – such as a Part, Chapter or section. A version of a provision is prospective either:

  1. where the provision (Part, Chapter or section) has never come into force or;
  2. where the text of the provision is subject to change, but no date has yet been appointed by the appropriate person or body for those changes to come into force.

Commencement Orders listed in the ‘Changes to Legislation’ box as not yet applied may bring this prospective version into force.

Changes to legislation:

There are currently no known outstanding effects for the Infrastructure (Wales) Act 2024, SCHEDULE 3. Help about Changes to Legislation

Close

Changes to Legislation

Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.

Prospective

(Introduced by section 145)

SCHEDULE 3E+WCONSEQUENTIAL AMENDMENTS AND REPEALS

This schedule has no associated Explanatory Notes

Harbours Act 1964 (c. 40)E+W

1(1)The Harbours Act 1964 is amended as follows.

(2)In section 14(1A), after paragraph (b) insert—

(c)section 20(2) of the Infrastructure (Wales) Act 2024 (exclusion of powers to authorise development to the extent that infrastructure consent is required);

(d)section 63(8) of that Act (exclusion of power to include ancillary provision in orders).

(3)In section 16(3A), after paragraph (b) insert—

(c)section 20(2) of the Infrastructure (Wales) Act 2024 (exclusion of powers to authorise development to the extent that infrastructure consent is required);

(d)section 63(8) of that Act (exclusion of power to include ancillary provision in orders).

Commencement Information

I1Sch. 3 para. 1 not in force at Royal Assent, see s. 147(2)

Highways Act 1980 (c. 66)E+W

2(1)The Highways Act 1980 is amended as follows.

(2)In section 10(2A), after “required)” insert “and section 20(3) of the Infrastructure (Wales) Act 2024 (exclusion of powers to make or confirm orders in relation to highways for which infrastructure consent required)”.

(3)In section 14(1A), after “required)” insert “and section 20(3) of the Infrastructure (Wales) Act 2024 (exclusion of powers to make or confirm orders in relation to highways for which infrastructure consent required)”.

(4)In section 16(3A), after “required)” insert “and section 20(3) of the Infrastructure (Wales) Act 2024 (exclusion of powers to make or confirm orders in relation to highways for which infrastructure consent required)”.

(5)In section 18(1A), after “required)” insert “and section 20(3) of the Infrastructure (Wales) Act 2024 (exclusion of powers to make or confirm orders in relation to highways for which infrastructure consent required)”.

(6)In section 106(4A), after “required)” insert “and section 20(3) of the Infrastructure (Wales) Act 2024 (exclusion of powers to make or confirm orders or schemes in relation to highways for which infrastructure consent required)”.

(7)In section 108(1A), after “required)” insert “and section 20(3) of the Infrastructure (Wales) Act 2024 (exclusion of powers to make or confirm orders in relation to highways for which infrastructure consent required)”.

(8)In section 110(1A), after “required)” insert “and section‍ 20(4) of the Infrastructure (Wales) Act 2024 (exclusion of power to authorise diversion of non-navigable waters in relation to highways for which infrastructure consent required)”.

(9)In section 329(1)—

(a)in the definition of “special road” after “2008” insert “or an infrastructure consent order under the Infrastructure (Wales) Act 2024”;

(b)in the definition of “trunk road” after “2008,” insert “or an infrastructure consent order under the Infrastructure (Wales) Act 2024,”.

(10)In section 337—

(a)omit “or” at the end of paragraph (a);

(b)after paragraph (b) insert—

(c)the carrying out of any development for which infrastructure consent is required under the Infrastructure (Wales) Act 2024 and for which infrastructure consent has not been given under that Act.

Commencement Information

I2Sch. 3 para. 2 not in force at Royal Assent, see s. 147(2)

Electricity Act 1989 (c. 29)E+W

3(1)The Electricity Act 1989 is amended as follows.

(2)In section 36—

(a)in subsection (1A), after “required)” insert “and section 20(1) of the Infrastructure (Wales) Act 2024 (exclusion of requirement for other consents for development for which infrastructure consent is required).”;

(b)in subsection (1B), after “2008” insert “and subsection (1) does not apply if the operation is authorised by an infrastructure consent order under the Infrastructure (Wales) Act 2024.”

(3)In section 37(2A)(b), after “planning permission” insert “, infrastructure consent order,”.

Commencement Information

I3Sch. 3 para. 3 not in force at Royal Assent, see s. 147(2)

Town and Country Planning Act 1990 (c. 8)E+W

4(1)The TCPA 1990 is amended as follows.

(2)In section 57(1A), after “required)” insert “and section 20(1) of the Infrastructure (Wales) Act 2024 (exclusion of requirement for planning permission etc. for development for which infrastructure consent is required)”.

(3)Omit sections 62D to 62L.

(4)In section 62M(4)(a) omit “, provided that the development to which it relates is not a development of national significance for the purpose of section 62D”.

(5)In section 62P—

(a)in subsection (1), omit “62D,”;

(b)in subsection (2), omit “62D or”.

(6)In section 62Q—

(a)in subsection (1)(a), omit “62D, 62F,”;

(b)in subsection (4)(a)—

(i)omit “section 62D or”;

(ii)for “the section in question” substitute “that section”;

(c)in subsection (4)(b)—

(i)omit “62F or”;

(ii)for “the section in question” substitute “that section”.

(7)In section 62R(1)—

(a)omit “62D,”;

(b)omit “62F,” in both places it occurs.

(8)In section 62S—

(a)omit “developments of national significance and”;

(b)after “Welsh Ministers” insert “under section 62M or 62O”.

(9)In section 70(1)(a), omit “section 62D(5),”.

(10)In section 70A(1)(a), as it applies in relation to Wales, omit “62D, 62F,”.

(11)In section 75A—

(a)in subsection (1)(a), omit “62D,”;

(b)in subsection (2), omit “62D,”;

(c)in subsection (3), omit “62D,”.

(12)In section 87, omit subsection (5).

(13)In section 88, omit subsection (11).

(14)In section 211 (preservation of trees in conservation areas)—

(a)in subsection (1A) after “consent” insert “or by infrastructure consent order”;

(b)in subsection (5A) after “consent” insert “or by infrastructure consent order”.

(15)In section 252—

(a)omit subsections (3A), (6B), (6C) and (6D);

(b)in subsection (12), omit the definition of “development of national significance”.

(16)In section 253(2)(aa), omit “62D, 62F,”.

(17)In section 257(4)(c), omit “62D, 62F,”.

(18)In section 284(3), omit paragraphs (aa) and (ab).

(19)In section 303—

(a)in subsection (1B)(a), omit “section 62D (developments of national significance),”;

(b)in subsection (1C)—

(i)omit paragraph (a);

(ii)in paragraph (b), omit “62D, 62F,”.

(20)In section 319B—

(a)in subsection (5A), omit “62D,”;

(b)in subsection (7), omit paragraph (za);

(c)in subsection (8A), omit “62D,”.

(21)In section 324(1), omit paragraph (bb).

(22)In section 333—

(a)in subsection (3F), omit paragraphs (b) and (c);

(b)in subsection (5C), omit “62L(9),”.

(23)In section 336(1) (interpretation), at the appropriate place, insert—

  • “infrastructure consent order has the meaning given in section 143 of the Infrastructure (Wales) Act 2024;.

(24)In Schedule 1A, in paragraph 8(2A), omit “62D, 62F,”.

(25)In Schedule 4D—

(a)in the Schedule title, omit “DEVELOPMENTS OF NATIONAL SIGNIFICANCE AND”;

(b)omit paragraph 1;

(c)in paragraph 3—

(i)omit “1 or” in both places it occurs;

(ii)omit “or consent” in both places it occurs;

(iii)omit “(as the case may be)”;

(d)in paragraph 4—

(i)omit “1 or” in both places it occurs;

(ii)omit “or consent” in both places it occurs;

(e)in paragraph 7, omit “or consent”;

(f)omit paragraph 8(2);

(g)in paragraph 9—

(i)omit “or consent”;

(ii)omit “paragraph 1 or”;

(h)in paragraph 10—

(i)omit “or consent” in both places it occurs;

(ii)omit “1 or”;

(i)in paragraph 11(1)—

(i)omit “or consent”;

(ii)omit “1 or”;

(j)in paragraph 11(2), omit “1 or”;

(k)in paragraph 12—

(i)omit “or consent”;

(ii)omit “1 or”;

(l)in paragraph 13—

(i)omit “or consent” in each place it occurs;

(ii)omit “1 or” in each place it occurs;

(iii)omit “, as the case may be,”;

(m)in paragraph 14, omit “or consent”.

(26)In Schedule 16, in Part 1, for “62D” substitute “62M”.

Commencement Information

I4Sch. 3 para. 4 not in force at Royal Assent, see s. 147(2)

Planning (Hazardous Substances) Act 1990 (c. 10)E+W

5(1)The Planning (Hazardous Substances) Act 1990 is amended as follows.

(2)In section 9(2)(c), after “permission in principle” insert “, infrastructure consent”.

(3)In section 10(1), after “specified planning permission” insert “, infrastructure consent”.

(4)In section 12, after subsection (2B) insert—

(2C)On making an order granting infrastructure consent in respect of development that would involve the presence of a hazardous substance in circumstances requiring hazardous substances consent, the person making the order may direct that hazardous substances consent shall be deemed to be granted, subject to such conditions (if any) as may be specified in the direction.

(5)In section 14(2)(b), after “planning permission”, in each place it appears, insert “, infrastructure consent”.

(6)In section 39, in the appropriate place, insert—

  • “infrastructure consent has the meaning given in section 143 of the Infrastructure (Wales) Act 2024;.

Commencement Information

I5Sch. 3 para. 5 not in force at Royal Assent, see s. 147(2)

New Roads and Street Works Act 1991 (c. 22)E+W

6(1)The New Roads and Street and Works Act 1991 is amended as follows.

(2)In section 6(1A), after “required)” insert “and section 20(3) (exclusion of powers to make or confirm orders in relation to highways for which infrastructure consent is required)”.

Commencement Information

I6Sch. 3 para. 6 not in force at Royal Assent, see s. 147(2)

Transport and Works Act 1992 (c. 42)E+W

7(1)The Transport and Works Act 1992 is amended as follows.

(2)In section 1(1A) (exclusions relating to orders as to railways, tramways etc.) after paragraph (b) insert—

(c)section 20(2) of the Infrastructure (Wales) Act 2024 (exclusion of powers to authorise development for which infrastructure consent is required);

(d)section 63(8) of that Act (exclusion of powers to include ancillary provision in orders).

(3)In section 3(1A) (exclusions relating to orders as to inland waterways etc.) after paragraph (b) insert—

(c)section 20(2) of the Infrastructure (Wales) Act 2024 (exclusion of powers to authorise development for which infrastructure consent is required);

(d)section 63(8) of that Act (exclusion of powers to include ancillary provision in orders).

Commencement Information

I7Sch. 3 para. 7 not in force at Royal Assent, see s. 147(2)

Coal Industry Act 1994 (c. 21)E+W

8(1)The Coal Industry Act 1994 is amended as follows.

(2)In section 53—

(a)in subsection (1), after “planning permission” insert “or infrastructure consent”;

(b)in subsection (2), after “such an application” insert “for planning permission, or where an examining authority or the Welsh Ministers consider any coal-mining proposals included in such an application for infrastructure consent,”;

(c)in subsection (4)—

(i)in paragraph (a), after “Town and Country Planning Act 1990” insert “, but “development” has the meaning given by section 133 of the Infrastructure (Wales) Act 2024 so far as it relates to coal-mining proposals included in an application for infrastructure consent”;

(ii)after the definition of ““development” and “planning permission””, insert—

  • examining authority” has the meaning given by section 40(7) of the Infrastructure (Wales) Act 2024;

  • “infrastructure consent has the meaning given by section 143 of the Infrastructure (Wales) Act 2024;.

Commencement Information

I8Sch. 3 para. 8 not in force at Royal Assent, see s. 147(2)

Planning and Compulsory Purchase Act 2004 (c. 5)E+W

9(1)The Planning and Compulsory Purchase Act 2004 is amended as follows.

(2)In section 60(3), for “development of national significance for the purposes of section 62D of the principal Act (development of national significance: applications to be made to Welsh Ministers)” substitute “a significant infrastructure project for the purposes of the Infrastructure (Wales) Act 2024”.

Commencement Information

I9Sch. 3 para. 9 not in force at Royal Assent, see s. 147(2)

Marine and Coastal Access Act 2009 (c. 23)E+W

10(1)The Marine and Coastal Access Act 2009 is amended as follows.

(2)In section 58, after subsection (5) insert—

(5A)This section does not apply to a decision on an application for infrastructure consent under the Infrastructure (Wales) Act 2024.

Commencement Information

I10Sch. 3 para. 10 not in force at Royal Assent, see s. 147(2)

Flood and Water Management Act 2010 (c. 29)E+W

11(1)The Flood and Water Management Act 2010 is amended as follows.

(2)In Schedule 3, in paragraph 7(3) after “(nationally significant infrastructure projects)” insert “or work requiring infrastructure consent under section 19 of the Infrastructure (Wales) Act 2024.”.

Commencement Information

I11Sch. 3 para. 11 not in force at Royal Assent, see s. 147(2)

Planning (Wales) Act 2015 (anaw 4)E+W

12(1)The Planning (Wales) Act 2015 is amended as follows.

(2)In section 1(6), for “to the Welsh Ministers. It makes provision” to the end substitute “either to the Welsh Ministers or a local planning authority”.

(3)Omit sections 19 to 22.

(4)In Schedule 4—

(a)in paragraph 5, omit “section 62D(5)”;

(b)in paragraph 6, omit “62D, 62F,”;

(c)in paragraph 7, in the inserted section 75A of the TCPA 1990—

(i)in subsection (1)(a), omit “62D,”;

(ii)in subsection (2), omit “62D,”;

(iii)in subsection (3), omit “62D,”;

(d)omit paragraphs 8 and 9;

(e)in paragraph 13, omit “62D, 62F,”;

(f)in paragraph 14(b), omit “62D, 62F,”;

(g)in paragraph 15(3)(c), omit paragraphs (aa) and (ab) inserted into section 284(3) of the TCPA 1990;

(h)in paragraph 18, in the inserted section 303 of the TCPA 1990—

(i)in subsection (1B)(a), omit “section 62D (developments of national significance),”;

(ii)in subsection (1C), omit paragraph (a) and in paragraph (b), omit “62D, 62F,”;

(i)in paragraph 20—

(i)in sub-paragraph (2), omit “62D,”;

(ii)in sub-paragraph (3), omit paragraph (za) inserted into section 319B(7) of the TCPA 1990;

(iii)in sub-paragraph (4), in subsection (8A) inserted into section 319B of the TCPA 1990, omit “62D,”;

(j)in paragraph 21, omit paragraph (bb) inserted into section 324(1) of the TCPA 1990;

(k)in paragraph 22, in sub-paragraph (2A) inserted into paragraph 8 of Schedule 1A to the TCPA 1990, omit “62D, 62F,”;

(l)in paragraph 23(2), for “62D” substitute “62M”.

Commencement Information

I12Sch. 3 para. 12 not in force at Royal Assent, see s. 147(2)

Infrastructure Act 2015 (c. 7)E+W

13(1)The Infrastructure Act 2015 is amended as follows.

(2)In Schedule 6, in paragraph 11(6), after paragraph (a) insert—

(aa)infrastructure consent under the Infrastructure (Wales) Act 2024;.

Commencement Information

I13Sch. 3 para. 13 not in force at Royal Assent, see s. 147(2)

Housing and Planning Act 2016 (c. 22)E+W

14(1)The Housing and Planning Act 2016 is amended as follows.

(2)In section 205(1), in the definition of “planning consent”—

(a)in paragraph (a), after “Act,” omit “or”;

(b)in paragraph (b), after “2008” insert— , or

(c)

infrastructure consent under the Infrastructure (Wales) Act 2024.

Commencement Information

I14Sch. 3 para. 14 not in force at Royal Assent, see s. 147(2)

Historic Environment (Wales) Act 2023 (asc 3)E+W

15(1)The Historic Environment (Wales) Act 2023 is amended as follows.

(2)In section 11 (requirement for works to be authorised by scheduled monument consent), after subsection (2) insert—

(3)This section is subject to section 20(1)(c)(i) of the Infrastructure (Wales) Act 2024 (class authorisations and authorisation by scheduled monument consent not required for development to the extent that infrastructure consent required).

(3)In section 58(4) (exception to offence of damaging certain monuments of special historical interest), after paragraph (b) insert—

(c)works for which infrastructure consent has been given under the Infrastructure (Wales) Act 2024.

(4)In section 88 (requirement for works to be authorised by listed building consent: exceptions), after subsection (3) insert—

(4)This section is subject to section 20(1)(c)(ii)of the Infrastructure (Wales) Act 2024 (authorisation by listed building consent not required for development to the extent that infrastructure consent is required).

(5)In section 118(2) (exception to offence of intentionally damaging listed building), after paragraph (e) insert—

(f)anything for which infrastructure consent has been given under the Infrastructure (Wales) Act 2024.

(6)In section 161 (requirement for demolition to be authorised by conservation area consent), after subsection (5) insert—

(6)This section is subject to section 20(1)(c)(iii) of the Infrastructure (Wales) Act 2024 (authorisation by conservation area consent not required for development to the extent that infrastructure consent required).”

Commencement Information

I15Sch. 3 para. 15 not in force at Royal Assent, see s. 147(2)

Back to top

Options/Help

Print Options

You have chosen to open The Whole Act

The Whole Act you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open The Whole Act as a PDF

The Whole Act you have selected contains over 200 provisions and might take some time to download.

Would you like to continue?

You have chosen to open the Whole Act

The Whole Act you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area. The revised version is currently only available in English.

Original (As Enacted or Made) - English: The original English language version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.

Original (As Enacted or Made) - Welsh:The original Welsh language version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.

Close

See additional information alongside the content

Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.

Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

Explanatory Notes

Text created by the Welsh Government department responsible for the subject matter of the Act to explain what the Act sets out to achieve and to make the Act accessible to readers who are not legally qualified. Explanatory Notes accompany all Acts of Senedd Cymru.

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources
Close

Timeline of Changes

This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.

Close

More Resources

Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • correction slips

Click 'View More' or select 'More Resources' tab for additional information including:

  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • links to related legislation and further information resources