Exhibit 1 shows that 4 of the project activities have a duration of 12 days.
Exhibit 2 shows that there are 8 hours in a work day.
Exhibit 3 is the exported .xer file.
Exhibit 4 shows that when the .xer file is exported the number of hours for the 12 day duration is 95 and not 96 whereas all the other durations are a multiple of 8.
Exhibit 5 confirms that clndr_id 178 is the “Corporate – Standard Full Time” calendar.
If you know the reason and solution for the above problem please would you let me to how much you would charge for enlightening me.
Dear Sir
Could you please send me the .xer file?
Exhibit 3 is a .txt file, not the .xer file.
I am an expert user of Primavera P6. I believe that I can fix this problem. just send me the .xer file
Best regards