fix: set multi-weekdays bug about issue-590 #592
Merged
Add this suggestion to a batch that can be applied as a single commit.
This suggestion is invalid because no changes were made to the code.
Suggestions cannot be applied while the pull request is closed.
Suggestions cannot be applied while viewing a subset of changes.
Only one suggestion per line can be applied in a batch.
Add this suggestion to a batch that can be applied as a single commit.
Applying suggestions on deleted lines is not supported.
You must change the existing code in this line in order to create a valid suggestion.
Outdated suggestions cannot be applied.
This suggestion has been applied or marked resolved.
Suggestions cannot be applied from pending reviews.
Suggestions cannot be applied on multi-line comments.
Suggestions cannot be applied while the pull request is queued to merge.
Suggestion cannot be applied right now. Please check back later.
What does this do?
the root cause of this issue is wrong logic. it should use the weekday to calculate instead of a job.RunCount.
if job.RunCount run over the setting days and it'll encounter an error
Which issue(s) does this PR fix/relate to?
fix #590
List any changes that modify/break current functionality
only fix bugs for schedule. if it executes though all weekdays one time, the behavior will change.
ex: user sets.
.Every(2).Weeks().Monday().Tuesday().At("10:00")
. then after executing Monday and Tuesday, the bug will show up. In the next round, after executing on Monday it will wait 2 weeks for execution on TuesdayHave you included tests for your changes?
yes, adjusted existing testing