It's premature to start working on this, but I wanted to jot down some notes collected from past conversations and experience on this topic (and I noticed we didn't have an issue for this yet).

A rescheduler is an agent that proactively causes currently-running Pods to be moved, so as to optimize some objective function for goodness of the layout of Pods in the cluster. (The objective function doesn't have to be expressed mathematically; it may just be a collection of ad-hoc rules, but in principle there is an objective function. Implicitly an objective function is described by the scheduler's predicate and priority functions.) It might be triggered to run every N minutes, or whenever some event happens that is known to make the objective function worse (for example, whenever a Pod goes PENDING for a long time.)

A rescheduler is useful because without a rescheduler, scheduling decisions are only made at the time Pods are created. But as the cluster layout changes over time, free "holes" are often produced that were not available when a Pod was initially scheduled. These holes are produced by run-to-completion Pods terminating, empty nodes being added by a node auto-scaler, etc. Moving already-running Pods into these holes may lead to a better cluster layout. A rescheduler might not just exploit existing holes, but also create holes by evicting Pods (assuming it knows they can reschedule elsewhere), as in free space defragmentation.

[Although alluded to above, it's worth emphasizing that rescheduling is the only way to make use of new nodes added by a cluster auto-scaler (unless Pods were already PENDING; but even then, it's likely advantageous to put more than just the previously PENDING Pods on the new nodes.)]

Because rescheduling is disruptive--it causes one or more already-running Pods to die when they otherwise wouldn't--a key constraint on rescheduling is that it must be done subject to disruption SLOs. There are a number of ways to specify these SLOs--a global rate limit across all Pods, a rate limit across a set of Pods defined by some particular label selector, a maximum number of Pods that can be down at any one time among a set defined by some particular label selector, etc. These policies are presumably part of the Rescheduler's configuration.

There are a lot of design possibilities for a rescheduler. To explain them, it's easiest to start with the description of a baseline rescheduler, and then describe possible modifications. The Baseline rescheduler

  • only kicks in when there are one or more PENDING Pods for some period of time; its objective function is binary: completely happy if there are no PENDING Pods, and completely unhappy if there are PENDING Pods; it does not try to optimize for any other aspect of cluster layout
  • is not a scheduler -- it simply identifies a node where a PENDING Pod could fit if one or more Pods on that node were moved out of the way, and then kills those Pods to make room for the PENDING Pod, which will then be scheduled there by the regular scheduler(s). [obviously this killing operation must be able to specify "don't allow the killed Pod to reschedule back to whence it was killed" otherwise the killing is pointless] Of course it should only do this if it is sure the killed Pods will be able to reschedule into already-free space in the cluster. Note that although it is not a scheduler, the Rescheduler needs to be linked with the predicate functions of the scheduling algorithm(s) so that it can know (1) that the PENDING Pod would actually schedule into the hole it has identified once the hole is created, and (2) that the evicted Pod(s) will be able to schedule somewhere else in the cluster.

Possible variations on this Baseline rescheduler are

  1. it can kill the Pod(s) whose space it wants and also schedule the Pod that will take that space and reschedule the Pod(s) that were killed, rather than just killing the Pod(s) whose space it wants and relying on the regular scheduler(s) to schedule the Pod that will take that space (and to reschedule the Pod(s) that were evicted)
  2. it can run continuously in the background to optimize general cluster layout instead of just trying to get a PENDING Pod to schedule
  3. it can try to move groups of Pods instead of using a one-at-a-time / greedy approach
  4. it can formulate multi-hop plans instead of single-hop

A key design question for a Rescheduler is how much knowledge it needs about the scheduling policies used by the cluster's scheduler(s).

  • For the Baseline rescheduler, it needs to know the predicate functions used by the cluster's scheduler(s) else it can't know how to create a hole that the PENDING Pod will fit into, nor be sure that the evicted Pod(s) will be able to reschedule elsewhere.
  • If it is going to run continuously in the background to optimize cluster layout but is still only going to kill Pods, then it still needs to know the predicate functions for the reason mentioned above. In principle it doesn't need to know the priority functions; it could just randomly kill Pods and rely on the regular scheduler to put them back in better places. However, this is a rather inexact approach. Thus it is useful for the rescheduler to know the priority functions, or at least some subset of them, so it can be sure that an action it takes will actually improve the cluster layout.
  • If it is going to run continuously in the background to optimize cluster layout and is going to act as a scheduler rather than just killing Pods, then it needs to know the predicate functions and some compatible (but not necessarily identical) priority functions One example of a case where "compatible but not identical" might be useful is if the main scheduler(s) has a very simple scheduling policy optimized for low scheduling latency, and the Rescheduler having a more sophisticated/optimal scheduling policy that requires more computation time. The main thing to avoid is for the scheduler(s) and rescheduler to have incompatible priority functions, as this will cause them to "fight" (though it still can't lead to an infinite loop, since the scheduler(s) only ever touches a Pod once).

The vast majority of users probably only care about rescheduling for three scenarios:

  1. Redistribute Pods onto new nodes added by a cluster auto-scaler
  2. Move Pods around to get a PENDING Pod to schedule
  3. Move Pods around when CPU starvation is detected on a node

Metadata

Labels

priority/awaiting-more-evidenceLowest priority. Possibly useful, but not yet enough support to actually get it done.sig/schedulingCategorizes an issue or PR as relevant to SIG Scheduling.

Type

No type

Projects

No projects

Relationships

None yet

Development

No branches or pull requests

Issue actions